Flomesta: "With this work we have managed to improve the safety of this rural road, avoid further subsidence, make repairs in the future for better conservation and we have responded to the needs of our neighbors and our neighbors."
It has also announced new improvements in the area
The Councilor for Agriculture, Livestock, Water, Environment and Rural Environment, Juan Mateo Flomesta, recently visited the new activities carried out on the rural road of 'La Cola', in the municipality of Campos del Río, some works that have concluded with success in record time, in less than two months.
The investment has amounted to 36,214.84 euros, co-financed with EAFRD funds by 63%, by the Ministry of Agriculture and Fisheries, Food and Environment by 11.10% and by the Autonomous Community by 25.90%.
The road, with a length of 791 meters and a variable width of between 4.5 and 5.5 meters, connects agricultural and livestock farms with population centers, regional roads and other rural roads of the town.
The mayor of Rural Environment, Juan Mateo Flomesta, explained that this road had for many years a firm with irregularities, blandones and subsidence, as well as narrow areas with danger of falls, so it was very necessary to repair.
"With this work we have managed to improve the safety of this rural road, avoid further subsidence, make repairs in the future for better conservation and we have responded to the needs of our neighbors and our neighbors who had been demanding these arrangements for years" .
The mayor has taken advantage of his visit to announce new actions that will be presented next and that are aimed at improving the area and its surroundings, while he has stated that "this Government Team will continue working on the repair of other rural roads, since These are very busy daily by farmers and ranchers and communicate the population center of Campos del Río with regional roads and farms that are an important engine of the economy in the municipality.
The integral preparation works of the road 'La Cola' consisted in the clearing and cleaning of the margins of the road in a width close to 0.20 m., Application of herbicide treatment in areas where it has not been possible to clear the vegetation of the path, opening of a ditch of land, 1 m.
of width and 0,5 m.
of depth in a length of 68 m., and installation of a concrete drainage pipe, with its chest and embouchure.
In areas where blandones are appreciated, the firm has been sanitized.
A reinforced concrete earth retaining wall with a running shoe has also been built.
In a specific area, where the road has a narrowing, the existing slope has been laid by the contribution of artificial gravel.
To do this, the topsoil has been removed and the seating surface for the filling has been prepared in order to compact it adequately.
Likewise, it has been increased from 5 manhole covers in order to leave them flush to the new rolling layer.
Finally, note that a pit and an existing pipe have been cleaned, a layer of regularization of the road surface has been placed with asphalt agglomerate, new vertical and horizontal signs have been placed on the road layout, and new road safety barriers have been installed. double wave accompanied by their corresponding abatements.
Source: Ayuntamiento de Campos del Río